Grace Bay Resorts Fetes The Point Construction Workers in Appreciation of Their Hard Work

9 minutes ago
3 min read

It was an atmosphere of appreciation, camaraderie and celebration at The Point Resort construction site in Grace Bay on Friday, November 20, as Grace Bay Resorts treated construction workers, contractors and consultants to an early afternoon of food, drinks and fellowship in recognition of their hard work.

The Grace  Bay Resorts and Projetech Team take time for a photo
The Grace  Bay Resorts and Projetech Team take time for a photo

Taking a welcome break from their construction duties in the early afternoon, the workers exchanged their tools for plates of food and refreshing beverages, enjoying a variety of dishes and an assortment of drinks, as the developer expressed gratitude for their dedication to bringing the luxury resort project to fruition.


The appreciation event also provided an opportunity to celebrate significant construction milestones and the longstanding partnership between Grace Bay Resorts and construction company Projetech.


Grace Bay Resorts Director of Development Jamie Stoughton expressed satisfaction with the project's progress, noting that construction had advanced considerably over the past year.


“This time last year we were on the first floor. We've now poured our sixth floor earlier this month. We're now getting ready to pour the seventh floor before Christmas,” Stoughton disclosed.


He explained that the roof is expected to be installed between January and February 2027, while work continues on the casitas, spa, reception and back-of-house facilities.

The construction workers were treated to a variety of drinks
The construction workers were treated to a variety of drinks

Additionally, construction of a commercial building featuring retail spaces along Grace Bay Road is expected to commence before Christmas.


Stoughton estimated that the concrete structural frame is approximately 90 percent complete, with interior finishing already underway, including drywall installation on the second floor.


He reaffirmed that the development remains on course towards its targeted December 2027 opening.


Turning to the appreciation event, Stoughton emphasised the importance of recognising those responsible for the project's progress.


“Today is just saying thank you to Projetech and all the supporting consultants, contractors. Without them this wouldn't happen,” he declared.


Projetech owner Kyle Camaro also expressed satisfaction with the construction pace, highlighting the tremendous teamwork demonstrated since the project commenced approximately 18 months ago.


“Progress is going well. We're up at the sixth floor. Structure is flying along. Interior fit out is going along. Floors are down. Drywall is going in. Starting painting,” Camaro explained.


He added that mechanical, electrical and plumbing installations in the casitas are progressing, with those structures expected to be enclosed shortly.


“Great progress on schedule. Great team. Great morale. Very successful project for everybody around,” he remarked.


For his part, Projetech Managing Director Steve Thompson praised Grace Bay Resorts for consistently recognising the contributions of construction workers throughout their more than 25-year working relationship.


“They do an appreciation like this for all of the guys that are putting the hard work in to actually make it happen. And it's really appreciated,” Thompson said.


He stressed that such gestures strengthen relationships and contribute positively to workplace morale.


“It helps create such a good team spirit. And it helps with the progress and just general atmosphere on site,” he added.

The Point Construction workers waiting in line to served delectable meals
The Point Construction workers waiting in line to served delectable meals

Grace Bay Resorts Executive Vice President of Operations Thierry Grandsire also commended Projetech for maintaining excellent construction momentum.


“The site is moving fantastically, it's on time, even maybe ahead of time,” Grandsire declared.


“Everything's going well, smooth, and we are absolutely delighted. And we are looking forward to open on time.”